Schedule of Rates and Charges |
Outdoor Lighting Rates           (Effective
March 1, 2010)
|
| |
Mercury Vapor * |
| |
Watts |
Rated kWh |
Energy Charge ** |
Facility Charge |
Cost Per Month *** |
| |
175 |
70 |
$3.71 |
$2.71 |
$6.42 |
| |
400 |
155 |
$8.21 |
$4.06 |
$12.27 |
| |
1,000 |
378 |
$20.02 |
$6.98 |
$27.00 |
| |
High Pressure Sodium |
| |
Watts |
Rated kWh |
Energy Charge ** |
Facility Charge |
Cost Per Month *** |
| |
100 |
42 |
$2.22 |
$4.12 |
$6.34 |
| |
150 |
63 |
$3.34 |
$4.24 |
$7.58 |
| |
250 |
105 |
$5.56 |
$4.87 |
$10.43 |
| |
400 |
165 |
$8.74 |
$5.78 |
$14.52 |
| | |
|
Notes: |
|
* Mercury vapor fixtures are not offered for new service.
** Energy Charge: For each lamp size above, 5.297 cents (1) per rated kWh per month
(1) Includes TVA Fuel Cost Adjustment (FCA) of -0.587¢
*** An additional charge of $2.50 per pole will be made where one or more poles are required for the sole purpose of installing the outdoor light or lights.
|
| |
Rates vs. Fuel Cost Adjustment
Each month TVA will implement a
Fuel Cost Adjustment (FCA) that can fluctuate with TVA's fuel and purchased
power costs. Therefore, electric rates may increase or decrease based on the amount TVA pays for fuel and purchased power.
CUB rates are approved by the Board of Directors. These
rates reflect a pass-through of TVA's
FCA increase.
|
|
|
|
|